Inspection - Part of Quality Assurance or Control Quality?

One of my student posted this question today on Udemy "Pass PMP in 21 Days"

And It made me think that quality, out of all the knowledge area is the one, in which we think, we know but end up with wrong answers.

For instance  - This question:

Is inspection as a tool part of QC (Quality Control) Or a QA (Quality Assurance) Process?

Here is the answer which I posted - 

"Inspection is relevant in both Quality Assurance and Quality Control. I do understand that this is the most confusing aspect of quality management. However just keep in mind that inspection process happens in Quality Assurance (Also referred as Audit) and understand since this is part of executing process group, the deliverables are under progress (Direct and Manage project work). So Quality assurance focuses on process inspection in order to PREVENT defects.

Quality control is part of monitoring and Controlling process group. This is assumed that deliverables by the execution team is finished and now those deliverables needs to be tested before they can be produced for sign offs (to internal or external clients). (Check the ITTO of this process)

So in QC (or Control Quality) the inspection take place on completed deliverables. 

What does this imply? It imply that you need to refer to the question context and need to understand as the scenario represent preventive checks or corrective checks (as part of inspection), and then only select the right option.



I hope - you, who are reading this get a clarity on QA and QC process after reading the post..

Please leave your comments here, and I'll get back to you.

Comments

Popular posts from this blog

Critical Path Method (CPM) Simplified..

A critical path is the longest path in the network.  Each node which falls under critical path has zero or negative float (Slack). Now how do we calculate critical path?? Sample Node I’ve seen various illustrations having different way to calculate CPM, few are: -           The project starts on day 1. -           The project starts on day 0. Both the approaches give same results, however I liked the day 0 approach better, its simpler, easy and lesser room for errors. Example Figure 1 - Example  There are 3 steps to calculate CPM: 1. Forward Pass - To calculate the Early Start(ES) and Early Finish(EF) of node. 2. Backward Pass - To calculate Late Start (LS) and Late Finish(LF) of node. 3. Calculate Float and Thus CPM. The Forward Pass: Forward Pass Illustration We start from first Node or Start node. The works begin on day 0....

Inside PMP Study Guide

Relationship between Project, Program and Portfolio

Project, Program and Portfolio - What is the difference? There have been few discussions in my recent workshops as what is the difference between project, program and portfolio. Lets start from the term which is most clear to all: Project: A project is a temporary endeavor undertaken to create a unique product, service, or result A project could be: Creating a website,   Creating a building,  Organising a rally/party Program:  A group of related projects, subprograms, and program activities that are managed in a coordinated way to obtain benefits not available from managing them individually. Programs may include operations and support activities.. The program could be : Rolling out 3G  network across india. Creating and Implementing a new policy organisation wide  Election campaign for presidential elections across country Portfolio A portfolio is a component c...