Critical Path Method (CPM) Simplified..

A critical path is the longest path in the network.  Each node which falls under critical path has zero or negative float (Slack).

Now how do we calculate critical path??

Sample Node
I’ve seen various illustrations having different way to calculate CPM, few are:

-          The project starts on day 1.
-          The project starts on day 0.

Both the approaches give same results, however I liked the day 0 approach better, its simpler, easy and lesser room for errors.

Example

Figure 1 - Example

 There are 3 steps to calculate CPM:

1. Forward Pass - To calculate the Early Start(ES) and Early Finish(EF) of node.
2. Backward Pass - To calculate Late Start (LS) and Late Finish(LF) of node.
3. Calculate Float and Thus CPM.

The Forward Pass:

Forward Pass Illustration
We start from first Node or Start node.
The works begin on day 0. 

We’ll fill up information in highlighted boxes:

In forward pass, we calculate the Early Start and early finish date of activities.

Node A:

The activity starts on day zero, since A activity duration is for 5 days, the early finish will take  Early Start and duration i.e.:
A(EF) = A(ES)  + Duration
A (EF)= 0 + 5 = 5

Node  B:   

Since there is only one node which precedes activity B. The relationship is F->S. That means that activity B can start only when activity A ends. Hence
B (ES) = A (EF)  = 5
B(EF) = B(ES) + Duration =  5+ 5 = 10
Activity C:   
C(ES) = B(EF) = 10
C(EF) = C(ES) + Duration = 10+ 4 = 14

Node Z

Now node C leads to node Z, but can we calculate the Z(ES )??
NO we cannot since it has to wait for 2 more activities for it to start. i.e. 
Node Z cannot start till activity C, E and H are complete. So let’s complete the calculations of all activities before Z.

Activity D,E, G, H

The calculations are pretty simple (same as B) since they have only one predecessor.

Back to activity Z:

Since this is a merging node, i.e. many activities has to end before we begin activity Z,
Z has more than one predecessor.
Z can start only when all the activities which are merging at Z can close hence Z can only start when the last activity (activity having  most late EF completes)

Z(ES) = Max | C(EF) or E(EF) or H(EF) |
Z(ES) = Max | 14 or 28 or 20|
Z(ES) = 28
Z(EF) = 28 + 0 = 28.
Forward Pass Calculations




The Backward Pass:

Here we’ll start from the last node i.e. Z, 

we calculate the bottom 2 squares (late Start and late finish)

Node Z:

Since this is the last node, Z’s last finish date would be equal to earliest finish date of Z i.e.
Z(LF) = Z(EF) = 28
Z(LS) = Z(LF) – Duration
Z(LS) = 28 – 0 = 28

Node H

Node H has only one node preceding it in backward pass (node Z).  Hence
H(LF) = Z(LS)  = 28
H(LS) = H(LF) – H(Duration) = 28 – 8 = 20

Node E

Node E has only one node preceding it in backward pass (node Z).  Hence
E(LF) = Z(LS)  = 28
E(LS) = E(LF) – E(Duration) = 28 – 10 = 18

Node C

Node C has only one node preceding it in backward pass (node Z).  Hence
C(LF) = C(LS)  = 28
C(LS) = C(LF) – C(Duration) = 28 – 4 = 24

Node G and G calculations are exactly as simple node calculations

Node B

Since Node B is where most of the activities are merging in backward pass i.e. C, D and G, this is where we need to pay more attention. In backward pass the node B’s Latest Finish (LF) would be earliest or all the nodes  Late Start i.e.
B(LF) = Least | C(LS) or D(LS) or G(LS)|
B(LF) = Least | 24 or 10 or 18|
B(LF) = 10
B(LS) = B(LF) – B(Duration) = 10 -5 = 5

Node A

A(LF) = B(LF) = 5
A(LS) = A(LF) – A(Duration) = 5 - 5 = 0
Backward Pass

Calculating Total Float or Slack:

Total float

Total amount of time that a schedule activity may be delayed from its early start date without delaying the project finish date, or intermediary milestone. It is calculated using:
Activity (ES) – Activity (LS) or activity (EF) Activity(LF) – Both will give you same results.

Free Float

This is an amount of time that a schedule activity can be delayed without delaying the early start of any immediately following schedule activities.
E.g. – For activity C
C (Total Float) = C (LS) - C(ES)  = 24 – 10 = 14
C (Free Float) = ES of next activity – C(EF )
C (Free Float) = Z(ES) – C(EF ) = 28 -14 = 14

Now the Critical path

Calculate the Total float for all activities as per the formula. 

All nodes which have zero or negative float/slack forms the CRITICAL PATH.

Here we can see that the nodes:

A,B,D,E and Z forms the critical path.

Hope this is useful. Please do send me your comments/feedback at kavita.sh@gmail.com.

In case you like this you might want be interested to see following:
- You tube video at:  



Comments

  1. Node G and G calculations are exactly as simple node calculations channge this to Node d and G calculations are exactly as simple node calculations

    ReplyDelete
  2. thanks for the good simpler sample.

    ReplyDelete
  3. is it a good idea to illustrate all possible paths, add the duration, the one with the longest duration is the critical path?

    ReplyDelete
  4. kavita

    I was struggling a lot to undersatnd the fund of CPM, flot ,ES,EF LS LF, back ward and farward..Really you made very simple to me..Thanks a bundle...Sagar

    ReplyDelete
  5. Its a great explanation. You deserve the appreciation.

    ReplyDelete
  6. I´ll have a MBA exam tomorrow and you help me a lot with your simple explanation. Thanks a lot.

    ReplyDelete
  7. Great explanation, I'm going to use this information on the civil PE exam in October 2013

    ReplyDelete
  8. 今日期末試験があるので、このボローグが本当に分かりやすかったです。
    どもありがとうございます。

    ReplyDelete
  9. Kavita this is an excellent article and makes calculation very simple, thank you !

    ReplyDelete
  10. amazing explanation, even better than the one I got in my lecture

    ReplyDelete
  11. excellent ... very helpful

    ReplyDelete
  12. At IIL - PMP Prep training is designed to be delivered as 4-day workshop and will be called Project Management Certificate Program. Please Enrol on below dates:

    Delhi/NCR: 18-21 December 2014
    Mumbai: 18-21 December 2014
    Bangalore: 22-25 January 2015

    Regards
    Kanchan
    kanchan.dhar@iil.com

    ReplyDelete

Post a Comment

Thanks for your comments.

Popular posts from this blog

Inside PMP Study Guide

Relationship between Project, Program and Portfolio

Project, Program and Portfolio - What is the difference? There have been few discussions in my recent workshops as what is the difference between project, program and portfolio. Lets start from the term which is most clear to all: Project: A project is a temporary endeavor undertaken to create a unique product, service, or result A project could be: Creating a website,   Creating a building,  Organising a rally/party Program:  A group of related projects, subprograms, and program activities that are managed in a coordinated way to obtain benefits not available from managing them individually. Programs may include operations and support activities.. The program could be : Rolling out 3G  network across india. Creating and Implementing a new policy organisation wide  Election campaign for presidential elections across country Portfolio A portfolio is a component c...