Skip to main content

PMP Mathematics - Quick Book


Integration Management

Cash-Flow Analysis Techniques

Project Selection Criteria

What is it

Selection Mechanism

Payback Period
Period of time required to recoup the funds expended in an investment, or to reach the break-even point.
Select Lowest
Internal Rate of Return (IRR):
Think bank Interest rate
Internal portfolio rate at which the investment will produce results.
Select Highest
Net Present Value: 
Money now is more valuable than money later on.

Formula:
PV = FV/(1 + r)t 
Where
r  =interest rate
PV – Present Value
FV = Future Value
t = Time period
Select Highest

Remember the Formula!!
ROI
Return on Investment
Divide net profit by total assets
Select Highest
Benefit Cost Ratio
Benefit / Cost
Select Highest

Cost Management

Rough Order of Magnitude estimate (ROM) = -25% to +75%
Definitive estimate = -5% to +10%

Earned Value Management Formulas:

Name

Formula

What is it?

Interpretation

BAC
Budget at Completion
No formula
Approved Budget

PV
Planned Value
PV = BAC* Planned % Complete
What your schedule says you should have spent

EV
Earned Value
EV = BAC * Actual% Complete
How much of the project’s value you’ve really earned

AC
Actual Cost
No Formula
Spending on the projects – actual

SPI
Schedule Performance Index
SPI = EV/PV
Whether you’re behind or ahead of schedule
SPI >1  - Ahead of Schedule
SPI = 1 – As per Schedule
SPI < 1 – Behind Schedule
SV
Schedule Variance
SV = EV-PV
How much ahead or behind schedule you are

CPI
Cost Performance Index
CPI = EV/ AC
Whether you’re within your budget or not
CPI >1  - Under Planned Budget
CPI = 1 – On Budget
CPI < 1 – Over Planned Budget
CV
Cost Variance
CV = EV – AC
How much above or below your budget you are

EAC
Estimate at Completion


EAC = BAC/CPI

Mostly Used

The expected total cost of completing all work.
If the CPI is expected to be the same

EAC
Estimate at Completion

EAC=AC+BAC–EV

If future work will be accomplished at the planned rate


ETC

ETC = EAC - AC
The expected cost to finish remaining work

TCPI
To Complete performance Index
TCPI=(BAC-EV)/(BAC-AC)

The run rate required to win the match
(Run rate = spending rate)
(Target Runs = Approved Budget)









 Three-Point Estimates:

PERT Analysis                Also called BETA Distribution

Mean = (P + M + O)/3                

Triangular Distribution     Also called Average Distribution

Mean = (P + 4M + O)/ 6

Quality Management


1 Sigma = 68.26%
2 Sigma = 95.46%
3 Sigma = 99.73%
6 Sigma = 99.99%
Pareto Rule = 80/20

Communication Management:

Communication channels = n * (n-1)/2
Where n is the number of stakeholders

Procurement Management

Make or Buy Decision:

Make or Buy Decision: Select decision which result in lower cost or lower risks.

Comments

Popular posts from this blog

Critical Path Method (CPM) Simplified..

A critical path is the longest path in the network.  Each node which falls under critical path has zero or negative float (Slack). Now how do we calculate critical path?? Sample Node I’ve seen various illustrations having different way to calculate CPM, few are: -           The project starts on day 1. -           The project starts on day 0. Both the approaches give same results, however I liked the day 0 approach better, its simpler, easy and lesser room for errors. Example Figure 1 - Example  There are 3 steps to calculate CPM: 1. Forward Pass - To calculate the Early Start(ES) and Early Finish(EF) of node. 2. Backward Pass - To calculate Late Start (LS) and Late Finish(LF) of node. 3. Calculate Float and Thus CPM. The Forward Pass: Forward Pass Illustration We start from first Node or Start node. The works begin on day 0....

Is PMP difficult to Pass?

I was in a PMP workshop (PMP Preparation). It was for an organisation and in-house. Good, matured project managers from various streams including finance, operations and training domain were in the room. This was Day 1. People were all tensed up, and you could sense the tension in the atmosphere. I started with joke and a few activities before lunch and slowly people got relaxed. The next day - again same environment, the folks went back and opened PMBOK and felt very nervous and hence the anxiety in environment. Someone asked "Why should I sit for the examination - what are the advantages of being a PMP"?  Is this a question for Day 2?? I wanted to ask, "You tell me why are you in this workshop - what made you decide to spend your money and be part of this session?" But I guess that was just the anxiety speaking. The same person on Day 4 (Last day) came back and said : "I went through PMBOK and I felt like I can read this book and understand t...

Pass PMP in 21 Days - Online

2 Hours, 21 Days with Kavita Sharma. Get ready for the new PMP challenge.  New innovative class to give you required help and support towards PMP prep. More details here: http://passpmp21days.com/pmp-online-with-kavita-sharma/ Who is Kavita Sharma? Recognized as the Significant contributor for her skills and input in the latest version of PMBOK. Author of Pass PMP in 21 days series of books. Check here newly updated books.