Skip to main content

PMP Mathematics - Quick Book


Integration Management

Cash-Flow Analysis Techniques

Project Selection Criteria

What is it

Selection Mechanism

Payback Period
Period of time required to recoup the funds expended in an investment, or to reach the break-even point.
Select Lowest
Internal Rate of Return (IRR):
Think bank Interest rate
Internal portfolio rate at which the investment will produce results.
Select Highest
Net Present Value: 
Money now is more valuable than money later on.

Formula:
PV = FV/(1 + r)t 
Where
r  =interest rate
PV – Present Value
FV = Future Value
t = Time period
Select Highest

Remember the Formula!!
ROI
Return on Investment
Divide net profit by total assets
Select Highest
Benefit Cost Ratio
Benefit / Cost
Select Highest

Cost Management

Rough Order of Magnitude estimate (ROM) = -25% to +75%
Definitive estimate = -5% to +10%

Earned Value Management Formulas:

Name

Formula

What is it?

Interpretation

BAC
Budget at Completion
No formula
Approved Budget

PV
Planned Value
PV = BAC* Planned % Complete
What your schedule says you should have spent

EV
Earned Value
EV = BAC * Actual% Complete
How much of the project’s value you’ve really earned

AC
Actual Cost
No Formula
Spending on the projects – actual

SPI
Schedule Performance Index
SPI = EV/PV
Whether you’re behind or ahead of schedule
SPI >1  - Ahead of Schedule
SPI = 1 – As per Schedule
SPI < 1 – Behind Schedule
SV
Schedule Variance
SV = EV-PV
How much ahead or behind schedule you are

CPI
Cost Performance Index
CPI = EV/ AC
Whether you’re within your budget or not
CPI >1  - Under Planned Budget
CPI = 1 – On Budget
CPI < 1 – Over Planned Budget
CV
Cost Variance
CV = EV – AC
How much above or below your budget you are

EAC
Estimate at Completion


EAC = BAC/CPI

Mostly Used

The expected total cost of completing all work.
If the CPI is expected to be the same

EAC
Estimate at Completion

EAC=AC+BAC–EV

If future work will be accomplished at the planned rate


ETC

ETC = EAC - AC
The expected cost to finish remaining work

TCPI
To Complete performance Index
TCPI=(BAC-EV)/(BAC-AC)

The run rate required to win the match
(Run rate = spending rate)
(Target Runs = Approved Budget)









 Three-Point Estimates:

PERT Analysis                Also called BETA Distribution

Mean = (P + M + O)/3                

Triangular Distribution     Also called Average Distribution

Mean = (P + 4M + O)/ 6

Quality Management


1 Sigma = 68.26%
2 Sigma = 95.46%
3 Sigma = 99.73%
6 Sigma = 99.99%
Pareto Rule = 80/20

Communication Management:

Communication channels = n * (n-1)/2
Where n is the number of stakeholders

Procurement Management

Make or Buy Decision:

Make or Buy Decision: Select decision which result in lower cost or lower risks.

Comments

Popular posts from this blog

Critical Path Method (CPM) Simplified..

A critical path is the longest path in the network.  Each node which falls under critical path has zero or negative float (Slack). Now how do we calculate critical path?? Sample Node I’ve seen various illustrations having different way to calculate CPM, few are: -           The project starts on day 1. -           The project starts on day 0. Both the approaches give same results, however I liked the day 0 approach better, its simpler, easy and lesser room for errors. Example Figure 1 - Example  There are 3 steps to calculate CPM: 1. Forward Pass - To calculate the Early Start(ES) and Early Finish(EF) of node. 2. Backward Pass - To calculate Late Start (LS) and Late Finish(LF) of node. 3. Calculate Float and Thus CPM. The Forward Pass: Forward Pass Illustration We start from first Node or Start node. The works begin on day 0....

Inside PMP Study Guide

Relationship between Project, Program and Portfolio

Project, Program and Portfolio - What is the difference? There have been few discussions in my recent workshops as what is the difference between project, program and portfolio. Lets start from the term which is most clear to all: Project: A project is a temporary endeavor undertaken to create a unique product, service, or result A project could be: Creating a website,   Creating a building,  Organising a rally/party Program:  A group of related projects, subprograms, and program activities that are managed in a coordinated way to obtain benefits not available from managing them individually. Programs may include operations and support activities.. The program could be : Rolling out 3G  network across india. Creating and Implementing a new policy organisation wide  Election campaign for presidential elections across country Portfolio A portfolio is a component c...