Skip to main content

What is Critical Chain method?

Let me start by asking you a question..

How many of you have told your team that the project duration is 90 days when the total days to complete the project duration signed off with customer was 100 days?

Most of you have done this!!

Having 10 days to be with you in order to handle any delay - is that correct? 
Giving incorrect information to your team - is that ethically wrong?

NO, Actually unknowingly you've implemented Critical Chain Method by inducing something called "Project Buffer"

Project Buffer:

It is the buffer which you've kept with you in order to absorb any delay without compromising on the project end date (those 10 days)


The yellow activities which you see depicts buffer. 
A critical chain uses buffers to absorb any delay on your project . 
To absorb overall delay in any path is Project Buffer (Buffer kept before the end of the project)

Feeding Buffer:

There would be times when you know that any task/activity given to a particular resource would take only X amount of hours/days. But you know the resource might be occupied e.g. Customer acceptance testing (instead of keeping 2 days you keep 5 days for acceptance testing)
or a senior architect review - you know that the review would take only 4 hours but he is a senior resource and might be travelling and other activities are dependent on it so you keep 5 days for senior architect review.  It might happen that the senior guy may not do the review even after 5 days because you followed up only on 5th day about the review status..

Instead, if you would have given him 4 hours (by asking his availability) and to handle any delays would have kept 4 days as "Feeding buffer" you would have gained 3 things:
  1. Optimal follow up on the activities 
  2. Absorption of delay - meeting the deadline to start the next activity ( because you kept 4 days as buffer)
  3. Better estimation for your project and forcing projects for your organisation

So next time when you plan your project, implement critical chain as the best practice!!


Comments

Popular posts from this blog

Critical Path Method (CPM) Simplified..

A critical path is the longest path in the network.  Each node which falls under critical path has zero or negative float (Slack). Now how do we calculate critical path?? Sample Node I’ve seen various illustrations having different way to calculate CPM, few are: -           The project starts on day 1. -           The project starts on day 0. Both the approaches give same results, however I liked the day 0 approach better, its simpler, easy and lesser room for errors. Example Figure 1 - Example  There are 3 steps to calculate CPM: 1. Forward Pass - To calculate the Early Start(ES) and Early Finish(EF) of node. 2. Backward Pass - To calculate Late Start (LS) and Late Finish(LF) of node. 3. Calculate Float and Thus CPM. The Forward Pass: Forward Pass Illustration We start from first Node or Start node. The works begin on day 0....

Is PMP difficult to Pass?

I was in a PMP workshop (PMP Preparation). It was for an organisation and in-house. Good, matured project managers from various streams including finance, operations and training domain were in the room. This was Day 1. People were all tensed up, and you could sense the tension in the atmosphere. I started with joke and a few activities before lunch and slowly people got relaxed. The next day - again same environment, the folks went back and opened PMBOK and felt very nervous and hence the anxiety in environment. Someone asked "Why should I sit for the examination - what are the advantages of being a PMP"?  Is this a question for Day 2?? I wanted to ask, "You tell me why are you in this workshop - what made you decide to spend your money and be part of this session?" But I guess that was just the anxiety speaking. The same person on Day 4 (Last day) came back and said : "I went through PMBOK and I felt like I can read this book and understand t...

Pass PMP in 21 Days - Online

2 Hours, 21 Days with Kavita Sharma. Get ready for the new PMP challenge.  New innovative class to give you required help and support towards PMP prep. More details here: http://passpmp21days.com/pmp-online-with-kavita-sharma/ Who is Kavita Sharma? Recognized as the Significant contributor for her skills and input in the latest version of PMBOK. Author of Pass PMP in 21 days series of books. Check here newly updated books.